In short. Version 1 of ProcureLink is online. It is built from the CQI Committee’s proposal of 25 May 2026 and covers all four phases, so one Purchase Request can be followed from the department’s PPMP to payment. Phase 1 (requisition and funding) has the most detail, because the proposal recommends piloting it first. The tracking dashboard, the four analytics dashboards and the Procurement Monitoring Report are included. Every amount, threshold and time limit is a setting the BAC Secretariat or the MCC can change.
Prototype: https://brghgmc-procurelink.pages.dev (the first page shows "Version 1" in the small print at the bottom)
Questionnaire: https://brghgmc-procurelink-questionnaire.pages.dev
Sample data only. Every person, supplier and amount in the prototype is fictional. Please do not enter real supplier details, real contract amounts or real passwords.
| Status key | Done = built and tested · Partly = built with a stated limit · Open = not yet built or waiting on your answers |
| How it was tested | An automated check opened every screen for each of the 31 sample accounts (1,365 screens, no errors), then ran each workflow from start to finish: a PR through all four phases, a failed bidding and re-bid, a TWG failure moving to the next bidder, a rejected delivery and replacement, and a Supplemental PPMP request. It was repeated as if today were four different dates up to July 2027. Approving a PR, creating a new PR, the PPMP limit and the dashboards were also tried by hand in a browser. |
| Shared data | Everyone who opens the link sees the same sample data, and a change made on one device appears on the others within a few seconds. |
| The proposal asks for | Status | What Version 1 does |
| A PR may only use items in the department’s approved PPMP | Done | The End-User picks items from the department’s approved PPMP. The quantity still available is shown for each item, and Submit stays off while any line asks for more than what is left. |
| Items not in the PPMP go through a Supplemental PPMP | Done | When an item is missing or used up, the page offers a Supplemental PPMP request. It goes to the Department Head, then to Budget. Once approved, the item is added to the PPMP and can be requested. |
| A tracking number for every PR | Done | Numbers like PR-2026-11-001 (year, month, running number), given when the PR is submitted. |
| Department Head approval within 1 day | Done | Approve and sign, or return with a note. A returned PR goes back to the End-User to fix or cancel. |
| Budget/Finance CAF or OBR within 2 days, deducted from the department’s budget | Done | The Budget Officer chooses the fund cluster, types the OBR and CAF numbers, and certifies. The amount is obligated at once against that department’s budget. "Department Budgets" shows approved, obligated, paid and available amounts for each department and fund. |
| The proposal asks for | Status | What Version 1 does |
| The system suggests the mode of procurement from the ABC | Done | At or below ₱1,000,000 with standard items: Small Value Procurement; above that, or with non-standard items such as medical equipment: Public Bidding. The amount is a setting. The BAC Secretariat confirms or picks another mode with a reason. |
| The RFQ goes out to matching suppliers | Partly | The system picks the active suppliers registered for the item categories and "sends" the RFQ or Invitation to Bid. No real e-mail is sent: each message is kept in the E-mail Outbox (simulated) and in the supplier portal. |
| Bids are recorded and ranked; bids over the ABC are disqualified | Done | Suppliers quote through the portal, or the BAC Secretariat encodes sealed envelopes. Amounts stay hidden until the opening. At the opening, bids are ranked from lowest; any bid over the ABC is disqualified automatically. No eligible bid makes it a failed bidding. |
| TWG post-qualification; a failure moves to the next lowest bidder | Done | The TWG passes or fails the lowest bidder with a finding. A failure moves the evaluation to the next lowest. When no bidder is left, it becomes a failed bidding, and the BAC can re-bid or change the mode. |
| The proposal asks for | Status | What Version 1 does |
| A BAC Resolution drafted automatically | Done | Drafted from the abstract of bids and the TWG result, then signed by each BAC member in turn. |
| MCC approval and Notice of Award within 5 days | Done | The MCC approves (which issues the NOA) or returns the resolution to the BAC with a note. |
| Supplier conforme | Done | The winning supplier signs the conforme in the supplier portal (two sample supplier accounts are provided). For public bidding, the supplier also attaches the performance security there. |
| PO and Notice to Proceed within 5 days | Done | The Supply Section prepares the PO; the MCC signs the PO and NTP. |
| The proposal asks for | Status | What Version 1 does |
| Delivery logging | Done | The Supply Section logs the delivery receipt with the quantities delivered. |
| IAC line-by-line inspection and IAR | Done | The IAC accepts or rejects each line. A rejection sends a Notice of Rejection/Replacement (simulated) and waits for a new delivery. When every line is accepted, the IAR is signed and the items are added to the MMIS receipts list (simulated). |
| Disbursement bundle, DV and payment within 7 days | Done | All papers of the PR are gathered into one bundle for Accounting, which prepares the DV and records the payment reference. The PR then closes. |
| Printed documents | Partly | PR, CAF, RFQ, Abstract, BAC Resolution, NOA, PO, NTP, Delivery Receipt, IAR and DV print with the hospital letterhead. They are clear printouts, not yet copies of the official forms (question E4). |
| The proposal asks for | Status | What Version 1 does |
| Tracking dashboard: KPI ribbon, Kanban by phase, SLA watchlist | Done | Tiles for active PRs, overdue PRs and amounts; a board with one column per phase; and a watchlist coloured green (3 or more days left), yellow (2 days or less) and red (overdue). Each person sees what is waiting for them first. |
| A reason is required for overdue steps | Done | A red PR cannot move on until the person types why it is late. The reasons feed the delay dashboard. |
| SLA bottleneck dashboard (CQI) | Done | Average days per phase, the share of steps finished on time, a delay heatmap by office for the last six months, failed-bidding causes and the latest delay reasons. |
| Strategic and financial dashboard (MCC) | Done | PPMP burn rate, budget against actual by department, a fund reversion risk list (from October, funded PRs that are stuck or overdue), the MCC’s signing queue and the ten largest open contracts. |
| Supplier reliability | Done | On-time delivery rate, rejections and days to conforme for each supplier, with a list of suspended or flagged suppliers. |
| BAC operations | Done | Bidding success rate, bids per RFQ, TWG speed and the mix of procurement modes. |
| Procurement Monitoring Report filled in automatically | Partly | Filled from the PR records for each semester, with CSV download and print. The column layout follows our reading of the GPPB format; please confirm it (question E5). |
| Every amount, threshold and time limit can be changed | Done | Settings, for the BAC Secretariat and the MCC: the Small Value Procurement limit, each step’s days, the watchlist colours, fund clusters, item categories, modes and the reversion radar. Every change is in the Audit Trail. |
| Item | Status | Notes |
| Official form layouts | Open | Waiting for your answer on which forms must match exactly (question E4). |
| Rules under RA 12009 | Open | Version 1 follows the steps in the proposal, which cites RA 9184. If the hospital now follows RA 12009 (2024), the modes, thresholds and periods will be updated from your answers (section B). |
| Sign-in | Partly | You sign in by tapping a sample account. There are no passwords in this prototype. |
| Attachments | Partly | Attachment names are recorded (for example, the signed CAF), but files are not stored. |
| Calendar or working days | Partly | Time limits count calendar days for now (question C3). |
| Two people changing the same PR at once | Partly | The later save wins. |
| Opening bids before the deadline | Partly | A button marked "demo only" lets the BAC Secretariat open bids early, so a full cycle can be tried in one sitting. It will be removed later. |
On the first page, tap a person to sign in as them. A small number on an account shows how many items are waiting for that person. A good way to start is to follow one PR from beginning to end:
| Account | Role | Good for trying |
| Karen Dacillo | End-User, Emergency Medicine | New PR from the PPMP; try asking for more than the PPMP allows; a Supplemental PPMP request. |
| Dr. Noel Zamora | Department Head, Emergency Medicine | Approve or return a PR. |
| Estela Cabral | Budget Officer | CAF / OBR; Department Budgets. |
| Hernan Macaraig | BAC Secretariat | Confirm the mode, send the RFQ, encode and open bids, Settings, PMR. |
| Froilan Habana | TWG | Post-qualification pass or fail. |
| Aurora Lanuza and the other BAC members | BAC | Sign the BAC Resolution. |
| Dr. Ramon Valencia | Medical Center Chief | Approve the award, sign the PO and NTP, the financial dashboard. |
| Mylene Narvaez | Supplier (Kalinaw Medical Trading) | Quote on an open RFQ; sign a conforme. |
| Marissa Paglinawan | Supply Officer | Prepare the PO; log a delivery. |
| Leonardo Guevarra | IAC | Inspect line by line; reject a line to see the replacement flow. |
| Joselito Delfino | Accounting | Disbursement bundle, DV and payment. |
| Clarissa Obias | CQI Committee | The tracking dashboard and the SLA bottleneck dashboard. |
The sample data already holds about 40 PRs at every stage, including overdue ones, a failed bidding and a rejected delivery, so the dashboards have something to show from the start.